Consider a project having the following ten activities:
Optimistic Most likely Pessimistic
Immediate Time (o) Time (m) Time (p) Time
Activity Predecessors (weeks) (weeks) (weeks) Est.
A none 1 5 9 6
B A 6 6 6 5
C A 3 5 9 4
D A 2 4 6 3
E B, C 4 4 4 4
F D 4 7 8 6
G E 2 2 8 5
H E, F 7 8 9 8
I F 4 6 9 7
J G, H, I 3 5 7 5
a) Draw and AOA diagram.
b) Identifying due time of the critical path
c) Compute for te, Path total, , total time duration of the critical Path
d) Compute for z value, the Pz (Normal standard distribution) and plot in a graph and the expected time for each activity?