    Consider a project having the following ten activities:
    Optimistic Most likely Pessimistic

    Immediate Time (o) Time (m) Time (p) Time

    Activity Predecessors (weeks) (weeks) (weeks) Est.

    A none 1 5 9 6

    B A 6 6 6 5

    C A 3 5 9 4

    D A 2 4 6 3

    E B, C 4 4 4 4

    F D 4 7 8 6

    G E 2 2 8 5

    H E, F 7 8 9 8

    I F 4 6 9 7

    J G, H, I 3 5 7 5

    a) Draw and AOA diagram.

    b) Identifying due time of the critical path

    c) Compute for te, Path total, , total time duration of the critical Path

    d) Compute for z value, the Pz (Normal standard distribution) and plot in a graph and the expected time for each activity?

    Need fresh solution to this Assignment without plagiarism?? Get Quote Now

    Expert Answer

    Asked by: Anonymous
    Plagiarism Checked
    Answer Rating:
    4.6/5

    Plagiarism free Answer files are strictly restricted for download to the student who originally posted this question.

    Related Assignments

    //
    Our customer support team is here to answer your questions. You can send Assignments directly to support team.
    👋 Hi, how can I help?